2015 APRIL EITS Maintenance Weekend

Times are based in MST

EITS Maintenance Prep Activities

Stop Mail Order Timers prdmps1a/b/c/d @ 19:45 - 20:00

04/11/2015 19:45 - 04/11/2015 20:00

Stop Mail Order Timers prdmps1a/b/c/d @ 19:45 - 20:00

Tasked to Mail Order Production support -
Lakshmanan Chinnappan
(CORE TASK)

Verify Active Alerts @20:00 – 20:10

04/11/2015 20:00 - 04/11/2015 20:10

Verify Active Alerts @20:00 – 20:10

Task Assigned to ICC West
(CORE TASK)

Stop DMP Listeners on prdaws2a-d @ 20:45 - 20:55

04/11/2015 20:45 - 04/11/2015 20:55

Stop DMP Listeners on prdaws2a/b/c/d @ 20:45 - 20:55

Tasked to Application Architecture
Mel Celaya
(CORE TASK)

Stop CMP Listeners on prdpsf2a/b/c/d @ 20:45 - 20:55

04/11/2015 20:45:01 - 04/11/2015 20:55

Stop CMP Listeners on prdpsf2a/b/c/d @ 20:45 - 20:55

Tasked to Application Architecture
Vinod Saravana
(CORE TASK)

Stop MPS JVM's Nodeagent and DMGR on prdmps1a/b/c/d @ 20:45 - 20:55

04/11/2015 20:45:02 - 04/11/2015 20:55

Stop MPS JVM's Nodeagent and DMGR on prdmps1a/b/c/d @ 20:45 - 20:55

Tasked to Application Architecture
Noah Stern
Vinod Saravana

(CORE TASK)

Stop OMS JVM's Nodeagent and DMGR dalmor1/2/3/4 @ 20:45 - 20:55

04/11/2015 20:45:04 - 04/11/2015 20:55

Stop OMS JVM's Nodeagent and DMGR dalmor1/2/3/4 @ 20:45 - 20:55

Tasked to Application Architecture
Noah Stern
Vinod Saravana

(CORE TASK)

EITS Maintenance Shutdown

2015 APRIL EITS Maintenance Begins

04/11/2015 20:59

Post Internal & External Maintenance Pages prdehs1a-d prdihs1a-d @ 21:00 - 21:05

04/11/2015 20:59:02 - 04/11/2015 21:05

Post Internal and External Maintenance Pages prdehs1a/b/c/d prdihs1a/b/c/d @21:00 - 21:05

Tasked to ICC West

(CORE TASK)

Post CCA Maintenance Pages on prdpcp1a-1d @ 21:00 - 21:05

04/11/2015 20:59:02 - 04/11/2015 21:05

Post CCA Maintenance Pages on prdpcp1a-1d @ 21:00 - 21:05

Tasked to ICC West
(CORE TASK)

Stop Requested Applications on Alarm Point @ 21:00 - 21:15

04/11/2015 20:59:59 - 04/11/2015 21:15

Stop Requested Applications on Alarm Point @ 21:00 - 21:15

Tasked to Enterprise Monitoring Solutions
Virginia Lee
(CORE TASK)

Stop JVM's on XWS Servers on prdxws1a-d & prdxws2a-d @ 21:00 - 21:15

04/11/2015 21:00 - 04/11/2015 21:15

Stop JVM's on XWS Servers on prdxws1a/b/c/d and prdxws2a/b/c/d 21:00 - 21:15

Tasked to Web Infrastructure
Mel Celaya
(CORE TASK)

Stop Portal JVM's on prdptl2a/b/c/d @ 21:00 - 21:15

04/11/2015 21:00 - 04/11/2015 21:15

Stop Portal JVM's on prdptl2a/b/c/d @ 21:00 - 21:15

Dependent on Maintenance Pages being posted

Tasked to Application Architecture Portal
Laxman Soma
(CORE TASK)

Stop Application CCA on prdpcp1a - 1d @ 21:00 - 21:15

04/11/2015 21:00 - 04/11/2015 21:15

Stop Application CCA on prdpcp1a - 1d @ 21:00 - 21:15

Task assigned to Application Architecture Portal
Laxman Soma
(CORE TASK)

Stop JVM's on AWS Servers prdaws1a-d & prdaws2a-d @ 21:00 - 21:15

04/11/2015 21:00 - 04/11/2015 21:15

Stop JVM's on AWS Servers prdaws1a/b/c/d and prdaws2a/b/c/d @ 21:00 - 21:15

Tasked to Web Infrastructure
Mel Celaya
(CORE TASK)

Stop Applications Peoplesafe JVM's on prdpsf1a/1b & prdpsf2a-h @ 21:00 - 21:15

04/11/2015 21:00:30 - 04/11/2015 21:15

Stop Applications: Peoplesafe JVM's on prdpsf1a/1b & prdpsf2a-h @ 21:00 - 21:15

Tasked to Application Architecture
Vinod Saravana
(CORE TASK)

Stop Application Rebates on prdpsf1a/1b & prdpsf2a - h @ 21:00 - 21:15

04/11/2015 21:00:35 - 04/11/2015 21:15

Stop Application Rebates on prdpsf1a/1b & prdpsf2a - h @ 21:00 - 21:15
Task Assigned to Application Architecture
Vinod Saravana
(CORE TASK)

Stop Application: ECS JVM's on prdecs2a/b/c/d @ 21:00 - 21:15

04/11/2015 21:00:45 - 04/11/2015 21:15

Stop Application: ECS JVM's on prdecs1a/b/c/d @ 21:00 - 21:15

Tasked to Application Architecture
Vinod Saravana
(CORE TASK)

Stop Mail Order JVM's on prdmor2a/b/c/d @ 21:00 - 21:15

04/11/2015 21:00:47 - 04/11/2015 21:15

Stop Mail Order JVM's on prdmor2a/b/c/d @ 21:00 - 21:15

Tasked to Application Architecture
VInod Saravana
(CORE TASK)

Stop QL & DCU3 @ 21:00 - 21:15

04/11/2015 21:00:51 - 04/11/2015 21:45

Stop QL & DCU3 @ 21:00 - 21:15

Tasked to AZ Data Center

(CORE TASK)

Stop Application: FUSE on PRDESP1a/b @ 21:00 - 21:15

04/11/2015 21:00:59 - 04/11/2015 21:15

Stop Application: FUSE on PRDESP1a/b @ 21:00 - 21:15

Tasked to Application Architecture
Noah Stern
Vinod Saravana
(CORE TASK)

EITS Maintenance Window

UNIX AIX - LPAR FIRMWARE MOVE - C54676 @ 20:00 - 01:00

04/11/2015 20:00 - 04/12/2015 01:00

UNIX AIX - LPAR FIRMWARE MOVE - C54676

Servers impacted:
dalimg1b

paz1cladpa1b

paz1e1uspa1b

paz1e1vspa1b

prdcrd1a

prdcsd1a

prdcts1a

prddwz1a

prdecd1b

prdeds1a

prdeds1c

prdepd1b
prdfni4a

prdgtd1a

prdpcd1a

prdrmd1a

prdsfd1a

prdssd1a

prdsxd1a

prdszd1

prdudb3a

prdudb4a

prdudb5b

sazvio22a
sazvio22b

sysnim22

trnrac1a

Tasked to AIX Admin
John Figueroa and team

Unix AIX Patch Microstrategy servers - C56065 @ 21:15 - 01:00

04/11/2015 21:15 - 04/12/2015 01:00

Unix AIX Patch Microstrategy servers - C56065 @ 21:15 - 01:00

Servers Impacted:
prdmsi1a.caremarkrx.net
PROD
Microstrategy
prdmsi1b.caremarkrx.net
PROD
Microstrategy
prdmsw1a.caremarkrx.net
PROD
Microstrategy
prdmsw2a.caremarkrx.net
PROD
Microstrategy
prdmsw2b.caremarkrx.net
PROD
Microstrategy

Tasked to Jim Vanzandt

UNIX AIX OS patches & Atape drive upgrade - C57191 @ 21:15 - 01:00

04/11/2015 21:15 - 04/12/2015 01:00

UNIX AIX OS patches & Atape drive upgrade - C57191 @ 21:15 - 01:00

Servers Impacted:
Prdtsm1,
Prdtsm2,
Prdtsm1r and
Prdtsm8

Task Assigned to:
VijayAkumar Sathiyaseelan

UNIX AIX- Apply patches to AIX servers - C54680 @ 21:00 - 01:00

04/11/2015 21:15 - 04/12/2015 01:00

UNIX AIX- Apply patches to AIX servers - C54680 @ 21:00 - 01:00
Servers Impacted:

DWHPROD1
PRDDWZ1
PRDRGD1A
PRDSBD1A
PRDTSM7

Tasked to Unix AIX
Khan Mohammed

Oracle DBA - Apply January Security Patches - C56000 @ 21:15 - 01:00

4/11/2015 21:15 - 4/12/2015 01:00

Oracle DBA - Apply January Security Patches - C56000 @ 21:15 - 01:00
Servers Impacted:
prdpps1

Databases Impacted:
satprd, ceeprod, alptprod, fnpprod, pdmprod, soasvcp

Task Assigned to Mary Allen

EITS Maintenance Start-Up

Start QL & DCU3 @ 21:45 - 22:45

04/11/2015 21:45 - 04/11/2015 22:45

Start QL & DCU3 @ 21:45 - 22:45

Tasked to Mainframe Support
AZ Data Center

Production TEST & Training CTG Check @ 00:25 - 00:30

04/12/2015 00:25 - 04/12/2015 00:30

Production TEST & Training CTG Check 00:25 - 00:30

Tasked to ICC West
(CORE TASK)

Start Application: ECS on prdecs2a/b/c/d @ 00:30 - 00:45

04/12/2015 00:30 - 04/12/2015 00:45

Start Application: ECS on prdecs2a/b/c/d

Tasked to Application Architecture
????? ?????
(CORE TASK)

Dependent on CTG Check complete

Preliminary Application Shakeout of ECS @ 00:45 - 01:00

04/12/2015 00:45 - 04/12/2015 1:00

Preliminary Application Shakeout of ECS

Tasked to Josephine Hamilton/ Luo Zuo

Start Mail Order CICS V-Region @ 01:00 - 1:30

04/12/2015 1:00 - 04/12/2015 01:30

Start Mail Order CICS V-Region @ 01:00 - 01:30

Tasked to AZ Data Center

Verify Filenet backups are complete @ 01:00 - 1:30

04/12/2015 1:00 - 04/12/2015 1:30

Verify Filenet backups are complete

Tasked to Application Architecture
Vinod Saravana
(CORE TASK)

Start all JVM's in AWS/XWS prdaws1&2a-d & prdxws1&2 a-d @ 01:00 - 01:30

04/12/2015 1:00 - 04/12/2015 01:30

Start all JVM's in AWS/XWS prdaws1a/b/c/d, prdaws2a/b/c/d and prdxws1a/b/c/d, prdxws2a/b/c/d

Tasked to Web Infrastructure
Pat Przbysz
(CORE TASK)

Start OMS/MPS JVM's Nodeagent and DMGR on prdmps1a-d & dalmor1-4 @ 01:00 - 1:30

04/12/2015 1:00 - 04/12/2015 01:30

Start OMS/MPS JVM's Nodeagent and DMGR on prdmps1a/b/c/d & dalmor1/2/3/4

Tasked to Application Architecture
????? ?????
(CORE TASK)

Production CTG Check @ 01:00 - 01:30

04/12/2015 01:00 - 04/12/2015 01:30

Production CTG Check @ 01:00 - 01:30
Assigned to ICC West

(CORE TASK)

Start Portal JVM's on prdptl2a/b/c/d @ 01:00 - 01:30

04/12/2015 01:00 - 04/12/2015 01:30

Start Portal JVM's on prdptl2a/b/c/d @ 01:00 - 01:30

Assigned to Application Architecture Portal
George Meng
(CORE TASK)

Start Applications: Mail Order JVM's prdmor2a/b/c/d @ 01:00 - 01:30

04/12/2015 01:00 - 04/12/2015 01:30

Start Applications: Mail Order JVM's prdmor2a/b/c/d

Dependency: ECS up and verified

Tasked to Application Architecture
???? ????
(CORE TASK)

Start Application FUSE on PRDESP1a/b @ 01:00 - 01:30

04/12/2015 1:00 - 04/12/2015 01:30

Start Application FUSE on PRDESP1a/b

Tasked to Application Architecture
????? ?????
(CORE TASK)

Cycle JVM's on IVR Servers prdivr2a/b/c/d @ 01:00 - 01:30

04/12/2015 01:00 - 04/12/2015 01:30

CYCLE JVM's on IVR Servers prdivr2a/b/c/d @ 01:00 - 01:30

Dependency: Application ECS is up and validated

Tasked Web Infrastructure
????? ?????
(CORE TASK)

Start Mail Order Timers prdmps1a/b/c/d @ 1:00 - 1:30

04/12/2015 1:00 - 04/12/2015 01:30

Start Mail Order Timers prdmps1a/b/c/d
Task assigned to Mail Order Personnel

Start Application CCA on prdpcp1a - 1d @ 01:00 - 01:30

04/12/2015 1:00 - 04/12/2015 01:30

Start Application CCA on prdpcp1a - 1d @ 01:00 - 01:30

Task assigned to Application Architecture Portal
George Meng

Start Applications: Peoplesafe JVM's on prdpsf1a-h prdpsf2a - h @ 01:00 - 01:30

04/12/2015 1:00:01 - 04/12/2015 01:30

Start Applications: Peoplesafe JVM's on prdpsf1a-h prdpsf2a - h

Tasked to Application Architecture
Vinod Saravana
(CORE TASK)

Start Application Rebates on prdpsf1a/b prdpsf2a - h @ 01:00 - 01:30

04/12/2015 1:00:02 - 04/12/2015 01:30

Start Application Rebates on prdpsf1a/b prdpsf2a - h

Tasked to Application Architecture
????? ?????

Start Applications on Alarm Point @ 01:30 - 01:45

04/12/2015 01:30 - 04/12/2015 01:45

Start Applications on Alarm Point

Tasked to Enterprise Monitoring Solutions
Virginia Lee
(CORE TASK)

Verify Active Alerts @ 1:30 - 1:35

04/12/2015 1:30 - 04/12/2015 1:35

Verify Active Alerts @ 1:30 - 1:35

Tasked to ICC WEST

Remove Portal Internal Maintenance Page @ 01:30 - 01:35

04/12/2015 01:30 - 04/12/2015 1:35

Remove Portal Internal Maintenance Page

Dependency on Application Portal restarted

Tasked to ICC West

(CORE TASK)

EITS OQ and Turnover

Start DMP Lstnrs on prdaws2a-d @ 01:30 - 1:45

04/12/2015 1:30 - 04/12/2015 1:45

Start DMP Lstnrs on prdaws2a-d

Tasked to Internet Support
????? ?????
(CORE TASK)

Start CMP Listeners on prdpsf2a-d @ 1:30 - 1:45

04/12/2015 01:30 - 04/12/2015 01:45

Start CMP Listeners on prdpsf2a-d

Tasked to Application Architecture
????? ?????
(CORE TASK)

Application OQ and Validation @ 01:30 - 03:00

04/12/2015 1:30 - 04/12/2015 3:00

Application OQ and Validation @ 01:30 - 03:00

Tasked to Josephine Hamilton/TIER 1 Support

Remove CCA Maintenance Pages on prdpcp1a-1d @ 02:30 - 02:35

04/12/2015 02:30 - 04/12/2015 02:35

Remove CCA Maintenance Pages on prdpcp1a-1d @ 02:30 - 02:35

Task assigned to ICC West

Remove Portal External Maintenance Pages @ 02:30 - 02:35

04/12/2015 02:30 - 04/12/2015 02:35

Remove Portal External Maintenance Pages
@ 02:30 - 02:35
Tasked to ICC West

(CORE TASK)

2015 APRIL EITS Maintenance Completes

04/12/2015 03:00

2015 APRIL EITS Maintenance Completes