DCOps Milestone Chart

Major Events

Holidays, Team Vacations, Freezes, etc.

Today

03/26/2015

Procure Deploy Workflow - Jack

Complete Ticket Analysis

04/03/2015

Complete Q4FY15 ticket analysis for 75% of all submitted Jira hardware request tickets.

Identify Top 20% Problems

Apr 10, 2015 - May 9, 2015

Complete Qualitative Analysis

April 10, 2015

Survey all requestors, managers. What are their top challenges/problems faced with the procure to deploy process today?
NO SOLUTIONS

Identify Root Cause

04/24/2015

Perform fishbone analysis on top 20% problems

Identify Solutions

04/30/2015

Identify short and long term solutions

ECR migration