Shepard Looks Over V1 Design & Requests Design Revisions
04/01/2015 - 04/03/2015
KEYLAY Turns Client Feedback Into Revised V2 Template Designs
04/06/2015 - 04/10/2015
Shepard Looks Over V2 Design & Requests Small Revisions Before Programming Begins
04/13/2015 - 04/15/2015
KEYLAY Makes Final Round of Design Changes
04/16/2015 - 04/17/2015
Shepard Approves Final Site Design
04/20/2015 - 04/22/2015
Programming Phase
KEYLAY Programs the Homepage and Main Subpage Templates
04/23/2015 - 06/08/2015
Update Shepard on Programming Status
05/01/2015
Update Shepard on Programming Status / Discuss Any Questions or Issues That Evolve
05/08/2015
Update Shepard on Programming Status / Discuss Any Questions or Issues That Evolve
05/15/2015
Update Shepard on Programming Status / Discuss Any Questions or Issues That Evolve
05/22/2015
Update Shepard on Programming Status / Discuss Any Questions or Issues That Evolve
05/29/2015
Shepard Looks Over Test Website and Makes a List of Functionality Edits
06/08/2015 - 06/10/2015
Shepard Receives a Link to the Development Site
06/08/2015
KEYLAY Makes Requested Functionality Edits
06/11/2015 - 06/19/2015
Shepard Makes Final Edit Requests
06/22/2015 - 06/24/2015
KEYLAY Programs Client's Final Requests, Fixes Last Minute Bugs & Implements Tweaks
06/25/2015 - 06/30/2015
Shepard Site is Launched!
Launch the New Shepard Website!
07/01/2015
Content Management System Training
Sometime During This Week Do a Conference Call to Teach the Shepard Team How to Use the Admin Panel
07/06/2015 - 07/10/2015
30 Days of Service
Provide a one-time training session, by phone, to show the client how to use the CMS admin section of the site prior to release.
Fix or repair faulty coding due to a Shepard Exposition Services programming error for (30 days) post taking the site live.
(After 30 days our standard hourly rate will be quoted to repair any programming issues or website changes.)
Keep a zipped copy of your original site on file as an archive if you ever need future access