2015 MARCH EITS Maintenance Weekend

Times are based in MST *NOTE: Daylight Savings Adjustment occurs 3/9/2015 @ 01:00 MST*

EITS Maintenance Prep Activities

Stop Mail Order Timers prdmps1a/b/c/d @ 20:45 - 21:00

03/07/2015 20:45 - 03/07/2015 21:00

Stop Mail Order Timers prdmps1a/b/c/d @ 20:45 - 21:00

Tasked to Mail Order Production support -
Lakshmanan Chinnappan
(CORE TASK)

Stop DMP Listeners on prdaws2a-d @ 21:45 - 21:55

03/07/2015 21:45 - 03/07/2015 21:55

Stop DMP Listeners on prdaws2a/b/c/d @ 21:45 - 21:55

Tasked to Application Architecture
????? ?????
(CORE TASK)

Stop CMP Listeners on prdpsf2a/b/c/d @ 21:45 - 21:55

03/07/2015 21:45 - 03/07/2015 21:55

Stop CMP Listeners on prdpsf2a/b/c/d @ 20:45 - 20:55

Tasked to Application Architecture
?????? ??????
(CORE TASK)

Stop OMS JVM's Nodeagent and DMGR dalmor1/2/3/4 @ 21:45 - 21:55

03/07/2015 21:45 - 03/07/2015 21:55

Stop OMS JVM's Nodeagent and DMGR dalmor1/2/3/4 @ 21:45 - 21:55

Tasked to Application Architecture
????? ?????

(CORE TASK)

Verify Active Alerts @21:45 – 21:55

03/07/2015 21:45 - 03/07/2015 21:55

Verify Active Alerts @21:45 – 21:55

Task Assigned to ICC West
(CORE TASK)

Stop MPS JVM's Nodeagent and DMGR on prdmps1a/b/c/d @ 21:45 - 21:55

03/07/2015 21:45 - 03/07/2015 21:55

Stop MPS JVM's Nodeagent and DMGR on prdmps1a/b/c/d @ 21:45 - 21:55

Tasked to Application Architecture
????? ?????

(CORE TASK)

EITS Maintenance Shutdown

2015 MARCH EITS Maintenance Begins

03/07/2015 21:59

Post Internal & External Maintenance Pages prdehs1a-d prdihs1a-d @ 22:00 - 22:05

03/07/2015 21:59:02 - 03/07/2015 22:05

Post Internal and External Maintenance Pages prdehs1a/b/c/d prdihs1a/b/c/d @22:00 - 22:05

Tasked to ICC West

(CORE TASK)

Post CCA Maintenance Pages on prdpcp1a-1d @ 22:00 - 22:05

03/07/2015 21:59:02 - 03/07/2015 22:05

Post CCA Maintenance Pages on prdpcp1a-1d @ 22:00 - 22:05

Tasked to ICC West
(CORE TASK)

Stop Requested Applications on Alarm Point @ 22:00 - 22:15

03/07/2015 21:59:59 - 03/07/2015 22:15

Stop Requested Applications on Alarm Point @ 22:00 - 22:15

Tasked to Enterprise Monitoring Solutions
Virginia Lee
(CORE TASK)

Stop JVM's on XWS Servers on prdxws1a-d & prdxws2a-d @ 22:00 - 22:15

03/07/2015 22:00 - 03/07/2015 22:15

Stop JVM's on XWS Servers on prdxws1a/b/c/d and prdxws2a/b/c/d 22:00 - 22:15

Tasked to Web Infrastructure
????? ?????
(CORE TASK)

Stop Application CCA on prdpcp1a - 1d @ 22:00 - 22:15

03/07/2015 22:00 - 03/07/2015 22:15

Stop Application CCA on prdpcp1a - 1d @ 22:00 - 22:15

Task assigned to Application Architecture Portal
????? ?????
(CORE TASK)

Stop JVM's on AWS Servers prdaws1a-d & prdaws2a-d @ 22:00 - 22:15

03/07/2015 22:00 - 03/07/2015 22:15

Stop JVM's on AWS Servers prdaws1a/b/c/d and prdaws2a/b/c/d @ 22:00 - 22:15

Tasked to Web Infrastructure
????? ?????
(CORE TASK)

Stop Portal JVM's on prdptl2a/b/c/d @ 22:00 - 22:15

03/07/2015 22:00 - 03/07/2015 22:15

Stop Portal JVM's on prdptl2a/b/c/d @ 22:00 - 22:15

Dependent on Maintenance Pages being posted

Tasked to Application Architecture Portal
????? ?????
(CORE TASK)

Stop Applications Peoplesafe JVM's on prdpsf1a/1b & prdpsf2a-h @ 22:00 - 22:15

03/07/2015 22:00:30 - 03/07/2015 22:15

Stop Applications: Peoplesafe JVM's on prdpsf1a/1b & prdpsf2a-h @ 22:00 - 22:15

Tasked to Application Architecture
????? ?????

(CORE TASK)

Stop Application Rebates on prdpsf1a/1b & prdpsf2a - h @ 22:00 - 22:15

03/07/2015 22:00:35 - 03/07/2015 22:15

Stop Application Rebates on prdpsf1a/1b & prdpsf2a - h @ 22:00 - 22:15
Task Assigned to Application Architecture
????? ?????
(CORE TASK)

Stop Application: FUSE on PRDESP1a/b @ 22:00 - 22:15

03/07/2015 22:00:59 - 03/07/2015 22:15

Stop Application: FUSE on PRDESP1a/b @ 22:00 - 22:15

Tasked to Application Architecture
????? ?????
(CORE TASK)

Stop Application: ECS JVM's on prdecs2a/b/c/d @ 22:00 - 22:15

03/07/2015 22:01 - 03/07/2015 22:15

Stop Application: ECS JVM's on prdecs1a/b/c/d @ 22:00 - 22:15

Tasked to Application Architecture
????? ?????
(CORE TASK)

Stop Mail Order JVM's on prdmor2a/b/c/d @ 22:00 - 22:15

03/07/2015 22:01:01 - 03/07/2015 22:15

Stop Mail Order JVM's on prdmor2a/b/c/d @ 22:00 - 22:15

Tasked to Application Architecture
????? ?????
(CORE TASK)

Stop QL & DCU3 @ 22:00 - 22:45

03/07/2015 22:01:05 - 03/07/2015 22:45

Stop QL & DCU3 @ 22:00 - 22:45

Tasked to AZ Data Center

(CORE TASK)

EITS Maintenance Window

UNIX Solaris - Apply Solaris 9 Patches to XPE Servers @ 22:00 - 01:00

03/07/2015 22:00 - 03/08/2015 01:00

UNIX Solaris - Apply Solaris 9 Patches to XPE Servers

Servers Impacted: xpedbs1, xpedbs2, xpeint1, xpeint2, xpeweb1, xpeweb2, xpemgmt

Tasked to Unix Solaris James Vanzandt

Web Infrastructure - Retire WAS 6.1 app and web servers @ 22:15 - 01:00

03/07/2015 22:15 - 03/08/2015 01:00

Web Infrastructure - Retire WAS 6.1 app and web servers

Servers Impacted: dalihs1, dalihs2, prdehs1a, prdehs1b, prdehs1c, prdehs1d, prdihs1a, prdihs1b, prdihs1c, prdihs1d, prdihs1a.coe

Task Assigned to Mel Celaya

UNIX AIX - LPAR & LPM Move - C52829 @ 22:15 - 01:00

03/07/2015 22:15 - 03/08/2015 01:00

UNIX AIX - LPAR & LPM Move - C52829

AIX Lpar ----prdudb1a, prdasd1a & prdemd1a-----------LPM move from 10B559P to 10B55AP FRAME.
firmware and memory upgrade on 10B559P frame is scheduled to April month and do not want the outage for these lpar for that activity. Hence would liek to move these lpar on frame 10B55AP frame.

and os patching to dalweb7 aix lpar

Tasked to AIX Admin
John Figueroa and team

QL DCU3 IPL PHX3 @ 22:45 - 01:00

03/07/2015 22:45 - 03/08/2015 01:00

QL IPL ACTIVITIES @ 22:45 - 01:00

Tasked to MQ Support & AZ Data Center
Christina Maldonado, Reid Solar, Scott Pearson
(CORE TASK)

Daylight Savings Time Adjustment @ 1:00 AM CST

03/08/2015 01:00

Daylight Savings Time Adjustment @ 1:00 AM CST

EITS Maintenance Start-Up

Start QL & DCU3 @ 22:45 - 23:45

03/07/2015 22:45 - 03/07/2015 23:45

Start QL & DCU3 @ 22:45 - 23:45

Tasked to Mainframe Support
AZ Data Center

Start Application: ECS on prdecs2a/b/c/d @ 00:30 - 00:45

03/08/2015 00:30 - 03/08/2015 00:45

Start Application: ECS on prdecs2a/b/c/d

Tasked to Application Architecture
????? ?????
(CORE TASK)

Preliminary Application Shakeout of ECS @ 00:45 - 01:00

03/08/2015 00:45 - 03/08/2015 1:00

Preliminary Application Shakeout of ECS

Tasked to Josephine Hamilton/TIER 1

Start Applications: Mail Order JVM's prdmor2a/b/c/d @ 01:00 - 01:30

03/08/2015 01:00 - 03/08/2015 01:30

Start Applications: Mail Order JVM's prdmor2a/b/c/d

Dependency: ECS up and verified

Tasked to Application Architecture
???? ????
(CORE TASK)

Production CTG Check @ 01:00 - 01:30

03/08/2015 01:00 - 03/08/2015 01:30

Production CTG Check @ 01:00 - 01:30
Assigned to ICC West

(CORE TASK)

Cycle JVM's on IVR Servers prdivr2a/b/c/d @ 01:00 - 01:30

03/08/2015 01:00 - 03/08/2015 01:30

CYCLE JVM's on IVR Servers prdivr2a/b/c/d @ 01:00 - 01:30

Dependency: Application ECS is up and validated

Tasked Web Infrastructure
????? ?????
(CORE TASK)

Start Mail Order CICS V-Region @ 01:00 - 1:30

03/08/2015 1:00 - 03/08/2015 01:30

Start Mail Order CICS V-Region @ 01:00 - 01:30

Tasked to AZ Data Center

Start Portal JVM's on prdptl2a/b/c/d @ 01:00 - 01:30

03/08/2015 01:00 - 03/08/2015 01:30

Start Portal JVM's on prdptl2a/b/c/d @ 01:00 - 01:30

Assigned to Application Architecture Portal
George Meng
(CORE TASK)

Start Application CCA on prdpcp1a - 1d @ 01:00 - 01:30

03/08/2015 1:00 - 03/08/2015 01:30

Start Application CCA on prdpcp1a - 1d @ 01:00 - 01:30

Task assigned to Application Architecture Portal
George Meng

Start OMS/MPS JVM's Nodeagent and DMGR on prdmps1a-d & dalmor1-4 @ 01:00 - 1:30

03/08/2015 1:00 - 03/08/2015 01:30

Start OMS/MPS JVM's Nodeagent and DMGR on prdmps1a/b/c/d & dalmor1/2/3/4

Tasked to Application Architecture
????? ?????
(CORE TASK)

Verify Filenet backups are complete @ 01:00 - 1:30

03/08/2015 1:00 - 03/08/2015 1:30

Verify Filenet backups are complete

Tasked to Application Architecture
Vinod Saravana
(CORE TASK)

Start all JVM's in AWS/XWS prdaws1&2a-d & prdxws1&2 a-d @ 01:00 - 01:30

03/08/2015 1:00 - 03/08/2015 01:30

Start all JVM's in AWS/XWS prdaws1a/b/c/d, prdaws2a/b/c/d and prdxws1a/b/c/d, prdxws2a/b/c/d

Tasked to Web Infrastructure
Pat Przbysz
(CORE TASK)

Start Mail Order Timers prdmps1a/b/c/d @ 1:00 - 1:30

03/08/2015 1:00 - 03/08/2015 01:30

Start Mail Order Timers prdmps1a/b/c/d
Task assigned to Mail Order Personnel

Start Application FUSE on PRDESP1a/b @ 01:00 - 01:30

03/08/2015 1:00 - 03/08/2015 01:30

Start Application FUSE on PRDESP1a/b

Tasked to Application Architecture
????? ?????
(CORE TASK)

Start Applications: Peoplesafe JVM's on prdpsf1a-h prdpsf2a - h @ 01:00 - 01:30

03/08/2015 1:00:01 - 03/08/2015 01:30

Start Applications: Peoplesafe JVM's on prdpsf1a-h prdpsf2a - h

Tasked to Application Architecture
Vinod Saravana
(CORE TASK)

Start Application Rebates on prdpsf1a/b prdpsf2a - h @ 01:00 - 01:30

03/08/2015 1:00:02 - 03/08/2015 01:30

Start Application Rebates on prdpsf1a/b prdpsf2a - h

Tasked to Application Architecture
????? ?????

Verify Active Alerts @ 1:30 - 1:35

03/08/2015 1:30 - 03/08/2015 1:35

Verify Active Alerts @ 1:30 - 1:35

Tasked to ICC WEST

Remove Portal Internal Maintenance Page @ 01:30 - 01:35

03/08/2015 01:30 - 03/08/2015 1:35

Remove Portal Internal Maintenance Page

Dependency on Application Portal restarted

Tasked to ICC West

(CORE TASK)

Start Applications on Alarm Point @ 01:30 - 01:45

03/08/2015 01:30 - 03/08/2015 01:45

Start Applications on Alarm Point

Tasked to Enterprise Monitoring Solutions
Virginia Lee
(CORE TASK)

EITS OQ and Turnover

Production TEST & Training CTG Check @ 1:30 - 1:45

03/08/2015 01:30 - 03/08/2015 01:45

Production TEST & Training CTG Check

Tasked to ICC West
(CORE TASK)

Application OQ and Validation @ 01:30 - 03:00

03/08/2015 1:30 - 03/08/2015 3:00

Application OQ and Validation @ 01:30 - 03:00

Tasked to Josephine Hamilton/TIER 1 Support

Start CMP Listeners on prdpsf2a-d @ 1:30 - 1:45

03/08/2015 01:30 - 03/08/2015 01:45

Start CMP Listeners on prdpsf2a-d

Tasked to Application Architecture
????? ?????
(CORE TASK)

Start DMP Lstnrs on prdaws2a-d @ 01:30 - 1:45

03/08/2015 1:30 - 03/08/2015 1:45

Start DMP Lstnrs on prdaws2a-d

Tasked to Internet Support
????? ?????
(CORE TASK)

Remove CCA Maintenance Pages on prdpcp1a-1d @ 02:30 - 02:35

03/08/2015 02:30 - 03/08/2015 02:35

Remove CCA Maintenance Pages on prdpcp1a-1d @ 02:30 - 02:35

Task assigned to ICC West

Remove Portal External Maintenance Pages @ 02:30 - 02:35

03/08/2015 02:30 - 03/08/2015 02:35

Remove Portal External Maintenance Pages
@ 02:30 - 02:35
Tasked to ICC West

(CORE TASK)

2015 MARCH EITS Maintenance Completes

03/08/2015 03:00

2015 MARCH EITS Maintenance Completes