Fast Start Program

Review the current program, suggest changes, determine timeline needed to make the changes and deliver on time.

evaluation / recommendation

03/03/2015 - 03/05/2015
03/10/2015
04/01/2015
05/01/2015 - 05/11/2015

develop content

03/10/2015 - 03/12/2015
03/13/2015
03/13/2015 - 03/16/2015
03/17/2015 - 03/18/2015
03/17/2015

pdf print pieces (self printed)

04/01/2015 - 04/03/2015
04/03/2015 - 04/06/2015
04/06/2015

website

03/18/2015 - 03/19/2015
03/23/2015 - 03/31/2015
04/01/2015
04/02/2015 - 04/08/2015
04/08/2015

drip campaign

04/08/2015
04/10/2015

training

03/18/2015 - 03/19/2015
03/24/2015 - 03/31/2015

communications

03/18/2015 - 03/19/2015

Printed Material

03/17/2015 - 03/18/2015
04/14/2015
04/14/2015 - 04/17/2015
04/17/2015
04/21/2015 - 04/30/2015
04/21/2015
05/04/2015 - 06/30/2015

sales kit

04/14/2015 - 04/16/2015
04/28/2015
04/28/2015 - 04/29/2015
04/29/2015
05/04/2015 - 06/30/2015
07/01/2015 - 07/20/2015
07/23/2015 - 07/25/2015
07/23/2015

gamification

03/16/2015 - 03/20/2015
04/01/2015 - 04/30/2015
05/01/2015 - 05/31/2015
06/01/2015 - 06/30/2015
07/23/2015 - 07/25/2015

Soft Launch

04/09/2015

Hard launch

07/23/2015