Conner Residence (Copy)

Events

permitting, pre-construction approvals, temp utilities

12/5/2014 - 1/4/2015

Site work, footings excavation, rebar, pre-pour inspection

01/05/2015 - 01/19/2015

pour footings, block work, core inspection

01/19/2015 - 02/09/2015

under slab rough in, rough in inspection

02/09/2015 - 02/23/2015

foundation backfill, compaction, slab prep, slab inspection

02/23/2015 - 03/09/2015

Construct Masonry fireplaces and chimneys, install flue pipe

03/09/2015 - 03/30/2015

wood framing,hurricane hardware, install doors and windows, framing inspections

03/30/2015 - 07/06/2015

install foundation brick, build masonry steps, install brick above roof line on Chimneys

05/25/2015 - 07/06/2015

install ice and water shield

06/08/2015 - 06/15/2015

weather wrap exterior, install exterior siding, trim, Aeratis flooring

07/06/2015 - 11/09/2015

install metal roof

07/06/2015 - 07/27/2015

Rough in of mechanical, electric. low voltage, AV, gas and plumbing, rough in inspections

08/03/2015 - 10/26/2015

spray foam insulate, blower door test, install soundproofing

11/02/2015 - 11/16/2015

paint exterior

11/09/2015 - 01/11/2016

installation of drywall, prime interior walls, permanent power inspections and hook up, gas, water, waste final connections

11/16/2015 - 12/07/2015

installation of interior trim details, installation of stone floors, walls, ceilings

12/07/2015 - 03/07/2016

landscape and hardscape installation

01/04/2016 - 04/04/2016

paint interior walls, trim, cabinets

03/07/2016 - 05/09/2016

installation of cabinetry, installation of pre-finished flooring, installation of final pre painted trim

04/18/2016 - 05/09/2016

installation of counters, plumbing fixtures, lighting fixtures, appliances

05/09/2016 - 06/06/2016

punch out, certificate of occupancy

05/30/2016 - 06/20/2016