permitting, pre-construction approvals, temp utilities

12/5/2014 - 1/4/2015

Site work, footings, block

01/05/2015 - 02/09/2015

under slab rough in

02/09/2015 - 02/23/2015

foundation backfill, compaction, slab prep, pour slab

02/23/2015 - 03/09/2015

wood framing,hurricane hardware, install doors and windows

03/09/2015 - 06/15/2015

Construct Masonry fireplaces and chimneys, install flue pipe

03/09/2015 - 03/30/2015

install foundation brick, build masonry steps, install brick above roof line on Chimneys

05/04/2015 - 06/15/2015

install ice and water shield

05/18/2015 - 05/25/2015

weather wrap exterior, install exterior siding, trim, Aeratis flooring

06/15/2015 - 09/14/2015

install metal roof

06/15/2015 - 07/06/2015

Rough in of mechanical, electric. low voltage, AV, gas and plumbing

06/29/2015 - 08/31/2015

spray foam insulate, blower door test, install soundproofing

09/14/2015 - 09/21/2015

complete screen porches trim and framing

09/14/2015 - 10/12/2015

installation of drywall, prime interior walls

09/21/2015 - 10/12/2015

paint exterior

09/21/2015 - 11/23/2015

installation of interior trim details, interior stone floors, walls, ceilings

10/12/2015 - 01/25/2016

permanent power inspections and hook up, gas, water, waste final connections

10/12/2015 - 11/02/2015

landscape and hardscape installation

11/23/2015 - 02/22/2016

install cabinetry

12/28/2015 - 01/18/2016

paint interior walls, trim, cabinets

01/25/2016 - 03/21/2016

installation of pre-finished flooring, shoe mold

03/21/2016 - 04/18/2016

install counters, plumbing fixtures, lighting, appliances

03/21/2016 - 04/11/2016

punch out, certificate of occupancy