Preplanning (SPR N)

11/17/2014

QA, PM and Van or Bryan are involved.

The goal of this activity is to finalize User Stories for the next sprint and agree them with Manage.com team.

Bug fixing (SPR N-1)

11/17/2014 - 11/18/2014

Dev team is involved

Demo (SPR N-1)

11/18/2014 11:00 PM

The whole team, Fred, Van and Bryan participate.

Functionality for SPR N-1 is ready according to definition of done.

Planning (SPR N)

11/19/2014 - 11/19/2014 9:00 AM

The whole team participates in this.

SPR N could be started

11/19/2014

Sprint could be started when on the following conditions:

  • All user stories, planned for the Sprint are described in Confluence
  • All user stories, planned for this Sprint are added to JIRA into corresponding Sprint
  • Usage scenario is clarified with Manage.com team

Development (SPR N)

Nov 19, 2014 09:00am - 11/21/2014

Developers participate in this event

Auto-test preparation (SPR N)

Nov 19, 2014 09:00am - 11/21/2014

QA participates in this

User stories (SPR N+1)

Nov 19, 2014 09:00am - 11/21/2014

QA and PM are involved

By the end of Friday draft user stories for SPR N+1 (the next one, not the one dev team is working on), should be ready.

SPR N is developed

11/21/2014 11:59 PM

By the end of Friday all items included into Sprint are developed, ready for testing. They are move to testing and assigned to QA in JIRA.

Bug fixing (SPR N)

11/24/2014 - 11/25/2014

Dev team is involved

Preplanning (SPR N+1)

11/24/2014

QA, PM, Bryan or Van participate

The goal of this activity is to finalize User Stories for the next sprint and agree them with Manage.com team.

Demo (SPR N)

11/26/2014

The whole team, Fred, Van, Bryan participate

Functionality of SPR N is ready according to definition of done.