Utrullningsplan "Flyttprojekt2.0" Ver:01

Utrullningsplan första utkast

Traffic Studio/VT Rakel TL-Installation

09/26/2014 - 10/17/2014
09/27/2014 - 09/29/2014
10/05/2014 - 10/10/2014
10/13/2014 - 10/24/2014

KIC Installation

09/26/2014
09/26/2014 - 10/17/2014
09/29/2014 - 10/03/2014
10/02/2014 - 10/03/2014
10/06/2014 - 10/10/2014
10/13/2014 - 10/17/2014

NET Installation TS

10/06/2014 - 10/17/2014
10/13/2014 - 10/17/2014
10/20/2014 - 10/24/2014

Skylttester

09/14/2014 - 10/12/2014
09/28/2014 - 10/10/2014
09/28/2014 - 09/30/2014
09/28/2014 - 10/10/2014

TLI Rakel Installation

09/26/2014 - 10/10/2014
10/13/2014 - 10/24/2014

BLAB TRAPEZE

10/06/2014 - 10/10/2014
10/08/2014 - 10/24/2014

GS BUTLER

10/06/2014 - 10/17/2014
10/13/2014 - 10/24/2014

HASTUS (Keolis & Veolia)

RESEPLANERAREN

10/13/2014 - 10/24/2014