Test Timeline

testing csv file import

Events

Planning

Current State Analysis and Report

2/24/2014 - 5/3/2014

Planning

Template Development

3/4/2014 - 3/28/2014

Planning

Create document index (classification/taxonomy)

05/05/2014 - 8/1/2014

Planning

Collate and classify existing documents as per document index

6/2/2014 - 12/19/2014

Planning

Assign Team Roles

6/2/2014 - 8/26/2014

Planning

Inventory existing document staorage solutions

6/10/2014 - 7/9/2014

Planning

Select systems to analyse for interim controlled document library

7/1/2014 - 7/11/2014

Planning

Analyse inventory for relevant existing documents

7/10/2014 - 10/7/2014

Planning

Determine interim document control system

7/21/2014 - 9/30/2014

Planning

Work Flow Modelling

9/3/2014 - 9/9/2014

Planning

Controls and permissions modelling

9/3/2014 - 9/11/2014

Planning

Content Modelling

9/9/2014 - 9/11/2014

Planning

Meta Data modelling

9/16/2014 - 9/19/2014

Planning

Set up prototype solution for review

9/22/2014 - 9/30/2014

Planning

Send prototype links out for review and comment

10/3/2014 - 10/17/2014

Planning

Content Analysis and Migration

Set up interim document library

10/1/2014 - 12/12/2014

Content Analysis and Migration

Analysis and Interim Set Up

10/6/2014 - 10/31/2014

Planning

Plan docunument migration and migrate documents from current document systems and storage to the interim document control solution

11/3/2014 - 11/21/2014

Content Analysis and Migration

Review migrated documents for completeness

11/24/2014 - 12/3/2014

Content Analysis and Migration

Plan the development new documents as required

12/6/2014 - 12/20/2014

Content Analysis and Migration

Update and manage existing documents as required.

12/7/2014 - 12/21/2014

Content Analysis and Migration

Interim library completed

12/22/2014

Content Analysis and Migration