EITS Maintenance Prep Activities

Stop Mail Order Timers prdmps1a/b/c/d @ 7:45 - 8:00

08/09/2014 19:45 - 08/09/2014 20:00

Stop Mail Order Timers prdmps1a/b/c/d @ 7:45 - 8:00

Tasked to Mail Order Production support - Krishindu Chatterjee

(CORE TASK)

Stop DMP Lstners CMPClone1-4 on prdaws1a-d & prdaws2a-d @ 20:45 - 20:55

08/09/2014 20:45 - 08/09/2014 20:55

Stop DMP Listeners under CMPClone1/2/3/4 on prdaws1a/b/c/d and prdaws2a/b/c/d @ 20:45 - 20:55

Tasked to Application Architecture
Adisesha Morreddigari
(CORE TASK)

Stop MPS JVM's Nodeagent and DMGR on prdmps1a/b/c/d @ 20:45 - 20:55

08/09/2014 20:45 - 08/09/2014 20:55

Stop MPS JVM's Nodeagent and DMGR on prdmps1a/b/c/d @ 20:45 - 20:55

Tasked to Application Architecture
Ramesh Rajagopal
(CORE TASK)

Stop CMP Listeners prdpsf2a/b/c/d @ 20:45 - 20:55

08/09/2014 20:45 - 08/09/2014 20:55

Stop CMP Listeners prdpsf2a/b/c/d @ 20:45 - 20:55

Tasked to Application Architecture
Ramesh Rajagopal
(CORE TASK)

Stop OMS JVM's Nodeagent and DMGR dalmor1/2/3/4 @ 20:45 - 20:55

08/09/2014 21:45 - 08/09/2014 21:55

Stop OMS JVM's Nodeagent and DMGR dalmor1/2/3/4 @ 20:45 - 20:55

Tasked to Application Architecture
Ramesh Rajagopal
(CORE TASK)

EITS Maintenance Shutdown

EITS Maintenance Begins

08/09/2014 20:59

Stop Applications: Peoplesafe JVM's on prdpsf1a-b prdpsf2a-h @ 21:00 - 21:15

08/09/2014 21:00 - 08/09/2014 21:15

Stop Applications: Peoplesafe JVM's on prdpsf1a-b prdpsf2a-h @ 21:00 - 21:15

Tasked to Application Architecture
Ramesh Rajagopal

(CORE TASK)

Stop JVM's on XWS Servers on prdxws1a-d & prdxws2a-d @ 21:00 - 21:15

08/09/2014 21:00 - 08/09/2014 21:15

Stop JVM's on XWS Servers on prdxws1a/b/c/d and prdxws2a/b/c/d 21:00 - 21:15

Tasked to Web Infrastructure
Adisesha Morreddigari
(CORE TASK)

Stop Mail Order JVM's on prdmor2a/b/c/d @ 21:00 - 21:15

08/09/2014 21:00 - 08/09/2014 21:15

Stop Mail Order JVM's on prdmor2a/b/c/d @ 21:00 - 21:15

Tasked to Application Architecture
Ramesh Rajagopal
(CORE TASK)

Post Internal & External Maintenance Pages prdehs1a-d prdihs1a-d @ 21:00 - 21:05

08/09/2014 21:00 - 08/09/2014 21:05

Post Internal and External Maintenance Pages prdehs1a/b/c/d prdihs1a/b/c/d @21:00 - 21:05

Tasked to ICC West

(CORE TASK)

Stop Applications on Alarm Point

08/09/2014 21:00 - 08/09/2014 21:15

Stop Applications on Alarm Point @ 21:00 - 21:15

Tasked to Enterprise Monitoring Solutions
Virginia Lee
(CORE TASK)

Stop Application Rebates on prdpsf1a/b prdpsf2a - h @ 21:00 - 21:15

08/09/2014 21:00 - 08/09/2014 21:15

Stop Application Rebates on prdpsf1a/b prdpsf2a - h

Task Assigned to Application Architecture
Ramesh Rajagopal

(CORE TASK)

Stop Applications: ECS JVM's on prdecs2a/b/c/d @ 21:00 - 21:15

08/09/2014 21:00 - 08/09/2014 21:15

Stop Applications: ECS JVM's on prdecs1a/b/c/d and prdecs2a/b/c/d

Tasked to Application Architecture
Ramesh Rajagopal
(CORE TASK)

Stop QL & DCU3 @ 21:00 - 21:15

08/09/2014 21:00 - 08/09/2014 21:15

Stop QL & DCU3 @ 21:00 - 21:15

Tasked to AZ Data Center

(CORE TASK)

Stop JVM's on AWS Servers prdaws1a-d & prdaws2a-d @ 21:00 - 21:15

08/09/2014 21:00 - 08/09/2014 21:15

Stop JVM's on AWS Servers prdaws1a/b/c/d and prdaws2a/b/c/d @ 21:00 - 21:15

Tasked to Web Infrastructure
Adisesha Morreddigari
(CORE TASK)

Stop Portal JVM's on prdptl2a/b/c/d @ 21:00 - 21:15

08/09/2014 21:00 - 08/09/2014 21:15

Stop Portal JVM's on prdptl2a/b/c/d @ 21:00 - 21:15

Dependent on Maintenance Pages being posted

Tasked to Application Architecture Portal
George Meng
(CORE TASK)

Stop Application: Specialty Portal on prdepp1a-d @ 21:00 - 21:15

08/09/2014 21:00 - 08/09/2014 21:15

Stop Application: Specialty Portal on prdepp1a-d @ 21:00 - 21:15

Tasked to Application Architecture Portal
George Meng/Bill Peng

(CORE TASK)

Post Specialty Portal Maintenance Pages on prdehs2a-d @ 21:00 - 21:05

08/09/2014 21:00 - 08/09/2014 21:05

Post Specialty Portal Maintenance Pages on prdehs2a prdehs2b prdehs2c prdehs2d @ 21:00 - 21:15

Tasked to ICC West

(CORE TASK)

Validate Specialty Portal Maintenance Page Posted @ 21:05 - 21:10

08/09/2014 21:05 - 08/09/2014 21:10

Validate Specialty Portal Maintenance Page Posted @ 21:05 - 21:10

Tasked to Internet Support
Mel Celaya

(CORE TASK)

Stop Application: FUSE on PRDESP1a/b @ 21:05 - 21:15

08/09/2014 21:05 - 08/09/2014 21:15

Stop Application: FUSE on PRDESP1a/b @ 21:05 - 21:15

Tasked to Application Architecture
Noah Stern
(CORE TASK)

EITS Maintenance Window

UDBDBA ACE V10 Upgrade Window @ 21:00 - 00:00

08/09/2014 21:00 - 08/10/2014 00:00

UDB DBA ACE V10 Upgrade Window @ 21:00 - 00:00

Servers/Databases:PRDCSD1 - PACC, PAAT, DMI001, DMI002
Training copies of same.
PRDDWZ1 - PACCRPT,DMICCRPT

Curt Ollerer & Keith Thompson UDB DBA's

Unix AIX Firmware Upgrade 21:00 - 01:00

08/09/2014 21:00 - 08/10/2014

Unix AIX Firmware Upgrade 21:00 - 01:00

Upgrade firmware on frames 065D5E4, 065D5A4, 101B934, 101D592, 1036FD5, 10F5141U

Tasked to AIX Admin
John Figueroa

QL IPL ACTIVITIES @ 21:00 - 22:00

08/09/2014 21:00 - 08/09/2014 22:00

QL IPL ACTIVITIES @ 21:00 - 22:00

Tasked to MQ Support & AZ Data Center
Christina Maldonado, Mike Smith, & Joe Wolensky
(CORE TASK)

Unix Solaris Critical Patches @ 21:00 - 01:00

08/09/2014 21:00 - 08/10/2014 00:00

Unix Solaris Critical Patches @ 21:00 - 01:00

Servers: xpedbs1,xpedbs2,xpein
t1,xpeint2,xpeweb1,xoeweb2,xpemgmt

Jim Vanzandt

Oracle DBA Filenet Security Patch Window @ 21:10 - 23:30

08/09/2014 21:10 - 08/09/2014 23:30

Oracle DBA Filenet Security Patch Window @ 21:10 - 23:30

server = prdfis1a. database = fnprod

Tasked to Oracle DBA & Unix Solaris
Carlo Tumibay and Jim Vanzandt

PBM Firewall Change Window 21:15 - 22:15

08/09/2014 21:15 - 08/09/2014 22:15

PBM Firewall Change Window 21:15 - 22:15

Tasked to ITSecOps_NetSec
Russ Schadd & Steven Kinson

Telecom Data VSS2 & VSS3 Upgrade @ 21:15 - 23:30

08/09/2014 21:15 - 08/09/2014 23:30

Telecom Data VSS2 & VSS3 Upgrade @ 21:15 - 23:30

Tasked to Telecom Data
Erik Westgaard & Pete Sellitto

EITS Maintenance Start-Up

Start QL & DCU3 @ 22:00 - 22:15

08/09/2014 22:00 - 08/09/2014 22:15

Start QL & DCU3 @ 22:00 - 22:15

Tasked to MQ Support and AZ DATA CENTER

(CORE TASK)

Start Mail Order CICS V-Region @ 22:00 - 22:15

08/09/2014 22:00 - 08/09/2014 22:15

Start Mail Order CICS V-Region @ 22:00 - 22:15

Tasked to AZ Data Center

Start Applications: ECS on prdecs2a/b/c/d @ 23:00 - 23:15

08/09/2014 23:00 - 08/09/2014 23:15

Start Applications: ECS on prdecs2a/b/c/d @ 23:00 - 23:15

Tasked to Application Architecture
Ramesh Rajagopal
(CORE TASK)

Start all JVM's in AWS/XWS prdaws1&2a-d & prdxws1&2 a-d @ 23:30 - 00:00

08/09/2014 23:30 - 08/10/2014 00:00

Start all JVM's in AWS/XWS prdaws1a/b/c/d, prdaws2a/b/c/d and prdxws1a/b/c/d, prdxws2a/b/c/d @ 23:30 - 00:00

Tasked to Web Infrastructure
Adisesha Morreddigari
(CORE TASK)

Verify Filenet backups are complete @ 23:30 - 23:45

08/09/2014 23:30 - 08/09/2014 23:45

Verify Filenet backups are complete @ 23:30 - 23:45

Tasked to Application Architecture
Bill Peng
(CORE TASK)

Stop JVM's on IVR Servers prdivr2a/b/c/d @ 23:30 - 23:45

08/09/2014 23:30 - 08/09/2014 23:45

Stop JVM's on IVR Servers prdivr2a/b/c/d @ 23:30 - 23:45

Dependency: Application ECS is up and validated

Tasked Web Infrastructure
Adisesha Morreddigari
(CORE TASK)

Start Application Rebates on prdpsf1a/b prdpsf2a - h @ 23:30 - 00:00

08/09/2014 23:30 - 08/10/2014 00:00

Start Application Rebates on prdpsf1a/b prdpsf2a - h @ 23:30 - 00:00

Tasked to Application Architecture
Ramesh Rajagopal

Production CTG Check @ 23:30 - 00:00

08/09/2014 23:30 - 08/10/2014 00:00

Production CTG Check
@ 23:30 - 00:00
Assigned to ICC West

(CORE TASK)

Start OMS/MPS JVM's Nodeagent and DMGR on prdmps1a-d & dalmor1-4 @ 23:30 - 00:00

08/09/2014 23:30 - 08/10/2014 00:00

Start OMS/MPS JVM's Nodeagent and DMGR on prdmps1a/b/c/d & dalmor1/2/3/4 @ 23:30 - 00:00

Tasked to Application Architecture
Ramesh Rajagopal
(CORE TASK)

Start Portal JVM's on prdptl2a/b/c/d @ 23:30 - 00:00

08/09/2014 23:30 - 08/10/2014 00:00

Start Portal JVM's on prdptl2a/b/c/d @ 23:30 - 00:00

Assigned to Application Architecture Portal
George Meng
(CORE TASK)

Start Application FUSE on PRDESP1a/b @ 23:30 - 00:00

08/09/2014 23:30 - 08/10/2014 00:00

Start Application FUSE on PRDESP1a/b 23:30 - 00:00

Tasked to Application Architecture
Noah Stern
(CORE TASK)

Start Applications: Peoplesafe JVM's on prdpsf1a-h prdpsf2a - h @ 21:30 - 00:00

08/09/2014 23:30 - 08/10/2014 00:00

Start Applications: Peoplesafe JVM's on prdpsf1a/b/c/d/e/f/g/h prdpsf2a - h @ 23:30 - 00:00

Tasked to Application Architecture
Ramesh Rajagopal
(CORE TASK)

Start Applications: Mail Order JVM's prdmor2a/b/c/d @ 23:30 - 00:00

08/09/2014 23:30 - 08/10/2014 00:00

Start Applications: Mail Order JVM's prdmor2a/b/c/d @ 23:30 - 00:00

Dependency: ECS up and verified

Tasked to Application Architecture
Ramesh Rajagopal
(CORE TASK)

Start Application Specialty Portal on PRDEPP1A-D @ 23:30 - 00:00

08/09/2014 23:30 - 08/10/2014 00:00

Start Application Specialty Portal on PRDEPP1A-D @ 23:30 - 00:00

Tasked to Application Architecture Portal
George Meng & Bill Peng
(CORE TASK)

Start JVM's on IVR Servers prdivr2a/b/c/d @ 23:45 - 00:00

08/09/2014 23:45 - 08/10/2014 00:00

Start JVM's on IVR Servers prdivr2a/b/c/d 23:45 - 00:00

Dependency: Application ECS is up and validated, and JVM's on IVR Servers have been stopped.

Tasked to Web Infrastructure
Adisesha Morreddigari
(CORE TASK)

Remove Portal Internal Maintenance Page @ 00:15 - 00:20

08/10/2014 00:15 - 08/10/2014 00:20

Remove Portal Internal Maintenance Page 00:15 - 00:20

Dependency on Application Portal restarted

Tasked to ICC West

(CORE TASK)

Start Applications on Alarm Point @ 00:15 - 00:30

08/10/2014 00:15 - 08/10/2014 00:30

Start Applications on Alarm Point @ 00:15 - 00:30

Tasked to Enterprise Monitoring Solutions
Virginia Lee
(CORE TASK)

Remove Specialty Maintenance Pages on PRDEHS2A-D @ 00:15 - 00:20

08/10/2014 00:15 - 08/10/2014 00:20

Remove Specialty Portal Maintenance Pages on prdehs2a prdehs2b prdehs2c prdehs2d @ 00:15 - 00:20

Tasked to ICC West
(CORE TASK)

Validate Specialty Portal Maintenance Pages Removed @ 00:20 - 00:25

08/10/2014 00:20 - 08/10/2014 00:25

Validate Specialty Portal Maintenance Pages Removed @ 00:20 - 00:25

Tasked to Internet Support
Mel Celaya
(CORE TASK)

EITS OQ and Turnover

Application OQ and Validation @ 00:00 - 01:00

08/10/2014 00:00 - 08/10/2014 01:00

Application OQ and Validation @ 00:00 - 01:00

Start DMP Lstnrs under CMPClone1-4 on prdaws1a-d & prdaws2a-d @ 00:40 - 00:55

08/10/2014 00:40 - 08/10/2014 00:55

Start DMP Listeners under CMPClone1/2/3/4 on prdaws1a/b/c/d and prdaws2a/b/c/d @ 00:40 - 00:55

Tasked to Internet Support
Adisesha Morreddigari
(CORE TASK)

Remove Portal External Maintenance Pages @ 00:55 - 01:00

08/10/2014 00:55 - 08/10/2014 01:00

Remove Portal External Maintenance Pages
@ 00:55 - 01:00
Tasked to ICC West

(CORE TASK)

August EITS Maintenance Ends and Turnover

08/10/2014 01:00

Production TEST & Training CTG Check @ 01:00 - 01:15

08/10/2014 01:00 - 08/10/2014 01:15

Production TEST & Training CTG Check @ 01:00 - 01:15

Tasked to ICC West
(CORE TASK)