Watkins Regional Park Master Plan Timeline

Overall Project Timeline

03/01/2014 - 08/01/2015

Pre-Planning

03/01/2014 - 08/31/2014

Procure Consulting Services

08/31/2014 - 10/31/2014

Develop Preliminary Recommendations

11/01/2014 - 04/30/2015

Key Stakeholder Engagement

11/01/2014 - 04/30/2015

Master Plan Finalized

05/01/2015 - 07/18/2015