Extended Project Timeline - 2014

Initial Project;

Introduced to EPQ

06/13/2014

Meet with supervisor to finish plans

06/16/2014 - 07/11/2014

Record Initial Planning

06/23/2014 - 06/25/2014

Project Proposal Part A

06/23/2014 - 06/27/2014

Create an action Plan for the Start of the project

06/25/2014 - 06/30/2014

Email Mrs Penycate with finished Plans

06/30/2014

Make sure that all Initial Work is completed by today

07/10/2014

Main Project;

Main Project/Research/Write Up Time

07/11/2014 - 09/08/2014

Background Research

07/11/2014 - 07/16/2014

Main Research

07/16/2014 - 07/23/2014

Ethical Issues

07/21/2014 - 07/24/2014

Plan Essay

07/23/2014 - 08/09/2014

Write a first Draft of Essay

08/01/2014 - 08/22/2014

Create Artefact

08/08/2014 - 09/19/2014

Check and Edit

08/22/2014 - 08/25/2014

Write a Second Draft of Essay

08/24/2014 - 09/08/2014

Mid-Project Review

09/08/2014 - 09/12/2014

Final Changes are made

09/08/2014 - 09/26/2014

Final Date to Drop Out

09/25/2014

Presentation

Prepare Presentation

09/08/2014 - 09/26/2014

Create Slides for Presentation

09/10/2014 - 09/15/2014

Final Presentation

10/06/2014 - 10/10/2014

Project Review to be completed - All work must be submitted for assessment

10/10/2014 - 10/20/2014

End of project review completed - NO EXTENSIONS

10/24/2014

Moderation Day

11/03/2014 - 11/06/2014