June Major Release Timeline

6/20/2014 Times based in CST

June Major Release Shutdown - 30 Minutes

June Application Release Begins @ 22:00

06/20/2014 21:59

Post Portal Maintenance Pages 22:00

06/20/2014 22:00 - 06/20/2014 22:10

Post Portal Maintenance Pages

Tasked to ICC West

Stop Application RxClaim 22:00

06/20/2014 22:00 - 06/20/2014 22:30

Stop Application RxClaim

Tasked to iSeries Team. Team will report when RxClaim is down

Front End Applications are stopped 22:10

06/20/2014 22:10 - 06/20/2014 22:30

Applications Include – Applications JVM’s-PBW/ADJ, LINKS, Portal, Peoplesafe, Drug, Retail, ECS, IVR, Ace, Gemini

Tasked to Application Architecture & Web Infrastructure

June Major Release Implementation Window - 4 Hours

RECAP Outage Window 22:00

06/20/2014 22:00 - 06/20/2014 23:00

RECAP Outage Window 22:00

POS Outage Window 22:30

06/20/2014 22:30 - 06/20/2014 23:30

POS Outage Window 22:30

22:30 - 23:30

Implement Database Changes 22:30

06/20/2014 22:30 - 06/21/2014 01:30

Implement Database Changes 22:30 - 01:30

Dependency: Front End Applications have been stopped

Implement Midrange Changes 22:30

06/20/2014 22:30 - 06/21/2014 01:30

Implement Midrange Changes 22:30 - 01:30

Dependency: Front End Applications have been stopped.

RxClaim Outage 22:30

06/20/2014 22:30 - 06/21/2014 2:30

RxClaim Outage 22:30 - 2:30

Systems will provide deployment status of implementation @ 00:30

Implement Mainframe Changes 00:30

06/21/2014 01:30 - 06/21/2014 02:30

Implement Mainframe Changes 01:30 - 02:30

Dependency: Database Changes have been complete

June Major Release Application Startup - 30 minutes

POS Restarted 23:30

06/20/2014 23:30 - 06/21/2014 00:00

POS Restarted 23:30

ECS & ECS Switch are started 00:30

06/21/2014 00:30 - 06/21/2014 01:00

Dependency: Deployment of all ECS code

Restart RxClaim 02:30

06/21/2014 02:30 - 06/21/2014 03:00

Dependency: RxClaim changes have been installed completely

Restart RxClaim 02:30

Tasked to iSeries Team. Team will report when RxClaim is up

Front End Applications are started 02:30

06/21/2014 02:30 - 06/21/2014 03:00

Dependency: Code Deployment Changes Complete

Applications Include – Applications JVM’s-PBW/ADJ, LINKS, Portal, Peoplesafe, Drug, Retail, ECS, IVR, Ace, Gemini

Tasked to Application Architecture & Web Infrastructure

Remove Portal Internal Maintenance Page 03:00

06/21/2014 03:00 - 06/21/2014 03:10

Dependency: Application Portal started & Portal has requested Internal Page removed

Remove Portal Internal Maintenance Page 03:00

Tasked to ICC West

June Major Release OQ & Turnover - 2 Hours

Front End Applications OQ 03:00

06/21/2014 3:00 - 06/21/2014 4:50

Front End Applications Validation Window 03:00

Dependency: Front End Applications started

RxClaim Application OQ 3:00

06/21/2014 3:00 - 06/21/2014 4:50

RxClaim Application Validation Window 3:00

Dependency: Application RxClaim started

Restart CMP Listeners @ 04:00

06/21/2014 04:00 - 06/21/2014 04:30

Restart CMP Listeners @ 04:00

Dependency: Request of CMP OQ resource.

Tasked to Application Architecture

Remove Portal External Maintenance Page 4:50

06/21/2014 4:50 - 06/21/2014 5:00

Remove Portal External Maintenance Page 4:50

Dependency: OQ Complete

Tasked to ICC West

June Major Release Complete 5:00

06/21/2014 5:00

June Major Release Complete 5:00

June Major Release Turnover