PPIS library database system workplan

Planning Phase

Create system vision

06/04/2014 - 06/10/2014

Business modeling

06/04/2014 - Approx. 06/13/2014

Understand business environment

Analysis Phase

Feasibility study

06/04/2014 - Approx. 06/17/2014

Document business requirements

06/04/2014 - Approx. 06/13/2014

Develop user interface dialogs

06/10/2014 - Approx. 06/20/2014

Design phase

Design support services architecture and development environment

06/13/2014 - Approx. 06/30/2014

Design database

06/14/2014 - Approx. 07/03/2014

Design software architecture

06/14/2014 - Approx. 06/30/2014

Design system and user interfaces

06/17/2014 - Approx. 07/07/2014

Design system security and controls

06/20/2014 - Approx. 07/11/2014

Testing Phase

Unit testing

06/24/2014 - 07/11/2014

Integration testing

06/30/2014 - 07/11/2014

User acceptance testing

07/03/2014 - 07/11/2014

Deployment Phase

Train users

07/14/2014 - 07/15/2014

Package and install components

07/14/2014 - 07/15/2014

Initialize data

07/14/2014 - 07/15/2014