Phase I : Efficiency Maximization

05/01/2014 - 07/31/2014

Purchasing of Materials and Equipment

07/01/2014 - 07/15/2014

ExCiTe Fund Results

07/01/2014

Main 2

Research into circuit systems and Grid-Tie Inverters

07/01/2014 - 07/15/2014

Phase I

Phase II : DSSC Applications

07/16/2014 - 11/30/2014

Lamps Shades

Work on lamp Shades

07/16/2014 - 08/31/2014

Mosaic

Work on Mosaic

09/01/2014 - 10/15/2014

Blinds

Work on Blinds

10/16/2014 - 11/30/2014