AustralianSuper - Implementation Plan and Estimated Timelines

High level Project Timeline

Phase

08/04/2014 - 07/31/2015

Impact Analysis Phase

08/04/2014 - 10/10/2014

Solution Definition Phase

08/04/2014 - 10/31/2014

Design Phase

10/06/2014 - 02/06/2015

Build&Unit Test

12/15/2014 - 04/03/2015

System Testing

02/02/2015 - 04/10/2015

System Intrgration Testing

03/18/2015 - 04/30/2015

UAT

03/18/2015 - 05/29/2015

Dress Rehearsals

04/06/2015 - 06/30/2015

Deployment

05/20/2015 - 07/10/2015

DR Deployment

06/29/2015 - 07/31/2015

Warranty

06/18/2015 - 08/31/2015