Work Period

1

Framing (4 Days)

05/15/2014 - 05/19/2014

2

Electrical (3 Days)

05/19/2014 - 05/22/2014

3

Dry Wall (7 Days)

05/22/2014 - 05/29/2014

4

Plastering (5 Days)

05/29/2014 - 06/03/2014

5

Hanging Ceil (2 Days)

06/03/2014 - 06/05/2014

6

Ordering Glass (10 Days)

06/03/2014 - 06/13/2014

7

Ordering Cupboard (45 Days)

06/03/2014 - 07/18/2014

8

Flooring (7 Days)

06/03/2014 - 06/10/2014

9

Base Board (2 Days)

06/10/2014 - 06/12/2014

10

Painting (5 Days)

06/12/2014 - 06/17/2014

11

Fixing Electrical (2 Days)

06/17/2014 - 06/19/2014

12

Fixing Cabinet (5 Days)

07/18/2014 - 07/23/2014

Cleaning (1 Day)

07/23/2014 - 07/24/2014