Unite Students

Pre Implementation

Go / No-Go for CRP

05/12/2014

Pre requirements

05/16/2014 - 05/20/2014

Pre requirements defined milestone

05/20/2014

Unite Students Implementation

Conference Room Pilot

05/24/2014 - 05/30/2014

Unite Students Implementation

05/24/2014 - 07/18/2014

Basic Technical Installation and Verification

05/26/2014 - 05/28/2014

Pilot, Bristol UK

05/29/2014 - 05/30/2014

Go / No-Go

05/30/2014

Viziya Implementation Plan

06/13/2014 - 07/05/2014

Project Kick-Off

06/13/2014 - 06/14/2014

Planning and Re-configuration

06/16/2014 - 06/18/2014

Unite Students Specific KPI requirements

06/18/2014 - 06/20/2014

Validation and Testing

06/24/2014 - 06/26/2014

Training

06/30/2014 - 07/04/2014

Project Wrap-up

07/04/2014 - 07/05/2014

Go Live & Support

Go Live Support

07/07/2014 - 07/08/2014

General Maintenance & Support by Project Team

07/08/2014 - 07/18/2014

Handover to Viziya Support Team

07/18/2014