RMS Project

VI Phase 1: TAP and Inf. Audit

Implementation Design

04/22/2014 - 05/02/2014

Partner Paperwork

04/23/2014 - 04/30/2014

Environment Validation Checklist

04/23/2014 - 04/30/2014

TAP Procurement and Shipment

04/28/2014 - 05/02/2014

Inf. Audit SOW/Procurement

04/30/2014 - 05/07/2014

TAP-in Training

05/05/2014 - 05/06/2014

Ship VI PAK or Rackable gear

05/26/2014 - 05/30/2014

TAP Implementation

05/26/2014 - 05/30/2014

Rack/Configure VI Equipment

06/02/2014 - 06/06/2014

Collect Data

06/03/2014 - 06/16/2014

Data Analysis & Report Creation

06/12/2014 - 06/24/2014

Present Findings

06/23/2014 - 06/24/2014