Artisan Server Infrastructure Refresh

Server Architecture Decision

HP/CISCO

01/01/2014 - 03/31/2014

Vendor meeting, team discussion,

Server Architecture Procurement

Test (145K)

04/01/2014 - 04/30/2014

7 Year Old Hardware, no redeployment plans

STG (50K)

09/01/2014 - 09/30/2014

7 Year Old Hardware, no redeployment plans

Production

01/01/2015 - 03/31/2015

Quote, build decisions

Server Architecture Deployment

Test

05/01/2014 - 05/31/2014

STG

10/01/2014 - 10/31/2014

Production

04/01/2015 - 06/30/2015

Server Redeployment

DR G8

08/01/2015 - 09/30/2015

4 Year Old Hardware, DR Deployment

Server Retirement

TST G5

06/01/2014 - 07/31/2014

7 Year Old Hardware

STG G5

11/01/2014 - 12/31/2014

7 Year Old Hardware

PRD G7

07/01/2015 - 07/31/2015

5 Year Old Hardware, no redeployment plans

DR G7

10/01/2015 - 12/31/2015

5 Year Old Hardware, no redeployment plans