Mathias Chen-Apt. 52C

Main

Architectual

02/17/2014 - 04/01/2014

Prepare architectural plans

Furniture, Flooring, Lighting, appliciances & fixtures

03/10/2014 - 12/31/2014

Placing orders throughout project.

Building approval

04/01/2014 - 04/30/2014

Obtain building approval

Permits

05/01/2014 - 05/31/2014

Obtain NYC building permit

Construction

06/01/2014 - 12/05/2014

Demo can commence, radiant floors in bathrooms, new wood flooring installed, marble in bathrooms,kitchen and outdoor area,central air,lighting trays,custom cabinetry & wire apartment for AV

Audio Visual Pre-wire

06/09/2014 - 06/13/2014

Place orders for all AV items and pre-wire.

Window treatments Install

12/01/2014 - 12/15/2014

Install last week of construction.

Audio Visual Install

12/01/2014 - 12/15/2014

Install AV

Furniture Delivery & Set up

12/15/2014 - 12/31/2014

Receive all furniture items & set up.