H&M Projects

FR050

Marc to deliver power supply

02/25/2014 - 02/26/2014

Practical site completion

02/26/2014

Release project implementation document

02/28/2014

Project complete and handed over

02/28/2014

PL001

Felix to install phase 2

03/05/2014 - 03/06/2014

Practical site completion

03/06/2014

Release project implementation document

03/07/2014

Project complete and handed over

03/07/2014

NL125

Signed PO received. Timer start

02/19/2014

Process order and dispatch

02/19/2014 - 03/07/2014

Felix to install on site

03/10/2014 - 03/11/2014

6-8 hours needed!

Release project implementation document

03/14/2014

Project complete and handed over

03/14/2014

FR179

Process order and dispatch. Not started!

02/24/2014 - 03/17/2014

Needed signed PO. Timer needs to start!

02/24/2014

Felix and team to install on site

03/17/2014 - 03/21/2014

Practical site completion

03/21/2014

Release project implementation document

04/04/2014

Project complete and handed over

04/04/2014

US080

Process order and dispatch

02/17/2014 - 03/10/2014

Signed PO received. Timer starts

02/17/2014

Kacy and team to install on site

03/24/2014 - 03/28/2014

Practical site completion

03/28/2014

Release project implementation document

04/01/2014

Project complete and handed over

04/01/2014

DE067

Signed PO received. Timer starts

03/03/2014

Process order and dispatch.

03/03/2014 - 03/24/2014

Felix and team to install on site

03/24/2014 - 03/28/2014

Practical site completion

03/28/2014

Release project implementation document

04/01/2014

Project complete and handed over

04/01/2014