May Major Release SEP (Dev/QU/UA) - Stream 1

DEV 1 Environment Initialization 3/26 - 4/1

03/26/2014 - 04/01/2014

SEP Activities - Code Devlopment 4/2 - 4/8

04/02/2014 - 04/08/2014

SIT 1 Environment Initialization 4/9 - 4/15

04/09/2014 - 04/15/2014

SEP Activities - Code Development, QA, UA 4/16 - 4/22

04/16/2014 - 04/22/2014

May Major Release Validation & Deployment

SIT 1 Pre-Regression 4/16 - 4/22

04/16/2014 - 04/22/2014

STP Initialization 4/23 - 4/25

04/23/2014 - 04/25/2014

STP Regression Testing 4/26 - 5/5

04/26/2014 - 05/05/2014

Performance Testing 5/6 - 5/13

05/06/2014 - 05/13/2014

Release Packaging 5/14 - 5/15

05/14/2014 - 05/15/2014

May Deployment 5/16

05/16/2014 - 05/17/2014

June Production Stability - Stream 1

May Production Stability 5/17 - 6/19

05/17/2014 - 06/19/2014