CMP Opening

CMP Planning and PO creation

02/03/2014 - 04/11/2014

[ ] Review data/phone drops with construction team
Order: [ ] Data/Phone T-1s, [ ] Network equipment, [ ] Phone equipment, [ ] Cabling, [ ] SS1, [ ] RBX (i/n), [ ] PCs, [ ] Printers, [ ] Handhelds, [ ] POS equipment, [ ] Tagnetics, [ ] IT Supplies
[ ] Create all POs
[ ] Book trips

Data/Phone Install

03/05/2014

[ ] All T-1s brought into store.

Network Setup

03/10/2014 - 03/14/2014

[ ] Network room install, [ ] Bring network online

CMP Equipment Setup

03/17/2014 - 04/14/2014

[ ] SS1 Setup, [ ] RBX Setup, [ ] PC Setup, [ ] HHU Setup, [ ] POS Setup

Tagnetics Install

04/07/2014 - 04/13/2014

[ ] TSC Install, [ ] TACs Install. [ ] Rails Install, [ ] Final walkthrough

SSI interview

04/08/2014

CMP Tagging/ Final Setup

04/15/2014 - 05/15/2014

[ ] SSI Starts, [ ] Final PC setup, [ ] Final POS setup
Tag whole store: [ ] Tagnetics, [ ] Yellow

SSI Starts

04/22/2014

1 SSI

04/29/2014 - 05/06/2014

Help from 1 additional SSI; weekdays only

2 SSI

05/07/2014 - 05/14/2014

Help from 2 additional SSI; weekdays only

Cashier Training

05/08/2014

POS should be 100% so FE can train

Opening support

05/15/2014 - 05/30/2014

Final store support after opening

CMP Opening Day

05/15/2014

CVL Opening

CVL Planning and PO creation

03/03/2014 - 05/23/2014

[ ] Review data/phone drops with construction team
Order: [ ] Data/Phone T-1s, [ ] Network equipment, [ ] Phone equipment, [ ] Cabling, [ ] SS1, [ ] RBX (i/n), [ ] PCs, [ ] Printers
[ ] Handhelds, [ ] POS equipment, [ ] Tagnetics, [ ] IT Supplies
[ ] Create all POs
[ ] Book trips

Data/Phone Install

04/16/2014

[ ] All T-1s brought into store

Network Setup

04/21/2014 - 04/25/2014

[ ] Network room install, [ ] Bring network online

CVL Equipment Setup

04/28/2014 - 05/28/2014

[ ] SS1 Setup, [ ] RBX Setup, [ ] PC Setup, [ ] HHU Setup, [ ] POS Setup

Tagnetics Install

05/19/2014 - 05/25/2014

[ ] TSC Install, [ ] TACs Install. [ ] Rails Install, [ ] Final walkthrough

SSI interview

05/20/2014

CVL Tagging/ Final Setup

05/30/2014 - 06/28/2014

[ ] SSI Starts, [ ] Final PC setup, [ ] Final POS setup
Tag whole store: [ ] Tagnetics, [ ] Yellow

SSI Starts

06/04/2014

1 SSI

06/11/2014 - 06/19/2014

Help from 1 additional SSI; weekdays only

2 SSI

06/20/2014 - 06/27/2014

Help from 2 additional SSI; Weekdays only

Cashier Training

06/20/2014

POS should be 100% so FE can train

Opening Support

06/28/2014 - 07/13/2014

Final store support after opening

CVL Opening Day

06/28/2014