Untitled timeline

Main

IGA Contract Executions

12/16/2013 - 12/17/2013

Sub-meter/Data Gather

12/18/2013 - 01/20/2014

Kick-Off

12/18/2013 - 12/19/2013

Lighting Sub Walks

01/02/2014 - 01/17/2014

Mech Sub Walks

01/07/2014 - 01/15/2014

Building Envelope Sub Walks

01/20/2014 - 01/23/2014

Initial Cost and Savings Finalized

01/27/2014 - 01/28/2014

Post 30% Scope Walks (if-needed)

02/03/2014 - 02/07/2014

Savings Reports Finalized

02/15/2014 - 02/22/2014

Cost Finalized

02/18/2014 - 02/24/2014

Submittals Approved

02/24/2014 - 02/27/2014

Review Meetings

30% Review

01/30/2014 - 01/31/2014

60% Review

02/07/2014 - 02/08/2014

90% Review

02/24/2014 - 02/25/2014

Final Report

03/03/2014 - 03/04/2014