Back working from hotel opening date
Back working from hotel opening date
08/01/2011
% complete
Date of launch
08/01/2011 - 08/31/2011
% complete
With everything in place, the systems & procedures will be tested. Basic training will be imparted to all the staff.
All HR related activities to be included in this layer
06/01/2011 - 07/31/2011
% complete
Offers will have to be given 1 month in advance. Only then will the staff arrive and will give us some time for training in August.
Will cover all procurement leading up to the opening of the hotel
04/03/2011 - 07/01/2011
% complete
All capital equipment - transformer, generator, AC units, kitchen equipment, laundry equipment, pumps, STP
04/03/2011 - 07/31/2011
% complete
Linen, crockery, cutlery, uniforms, food supplies, stationary etc.
All aspects related to running the hotel to be covered in this including - procedures, softwares, systems etc.
05/01/2011 - 06/30/2011
% complete
Everything that needs to set to get the hotel running smoothly.
06/01/2011 - 06/30/2011
% complete
Figuring out the pricing and distribution of rooms & other services.
04/20/2011 - 08/01/2011
% complete
Sales Tax, Excise, Service Tax, Luxury tax, PF, ESI
05/02/2011 - 09/01/2011
% complete
Classification & any other registrations
current - 07/15/2011
% complete
Pollution, Electricity, Police etc.
04/03/2011 - 09/01/2011
% complete
06/15/2011 - 09/01/2011
% complete
current - 09/01/2011
% complete
current - 07/01/2011
% complete
current - 08/01/2011
% complete
current - 08/31/2011
% complete