Soft Opening period

08/01/2011 - 08/31/2011

With everything in place, the systems & procedures will be tested. Basic training will be imparted to all the staff.

Hotel Opening

08/01/2011

Date of launch

Human Resources

All HR related activities to be included in this layer

Recruiting

06/01/2011 - 07/31/2011

Offers will have to be given 1 month in advance. Only then will the staff arrive and will give us some time for training in August.

Procurement

Will cover all procurement leading up to the opening of the hotel

Capital procurement

04/03/2011 - 07/01/2011

All capital equipment - transformer, generator, AC units, kitchen equipment, laundry equipment, pumps, STP

Operations procurement

04/03/2011 - 07/31/2011

Linen, crockery, cutlery, uniforms, food supplies, stationary etc.

Operations

All aspects related to running the hotel to be covered in this including - procedures, softwares, systems etc.

Operating procedures

05/01/2011 - 06/30/2011

Everything that needs to set to get the hotel running smoothly.

Revenue management

06/01/2011 - 06/30/2011

Figuring out the pricing and distribution of rooms & other services.

Legal & Regulatory

Taxation

04/20/2011 - 08/01/2011

Sales Tax, Excise, Service Tax, Luxury tax, PF, ESI

Tourism

05/02/2011 - 09/01/2011

Classification & any other registrations

Operational

current - 07/15/2011

Pollution, Electricity, Police etc.

Marketing

Tour operators

04/03/2011 - 09/01/2011

Corporates

06/15/2011 - 09/01/2011

Travellers

current - 09/01/2011

Construction

Interiors and finishing

current - 08/01/2011

Landscaping

current - 08/31/2011

Civil & Services

current - 07/01/2011