EDER 679: Final ProjectProfessional Development Modules for Teacher Technology Training |
Dates: 09/01/2010 - 09/03/2010
Duration: 2 days
Notes:
Meet to decide on modules to be developed, order and mode of delivery. Project vision and scope document.
Dates: =ENDOF("Module Development Plan") - 09/10/2010
Duration: 1 week
Notes:
Project Plan Finalization
Dates: =ENDOF("Project Plan") - 09/14/2010
Duration: 4 days
Notes:
Application is developed and submitted to administration.
Dates: =ENDOF("AISI Application") - 09/17/2010
Duration: 3 days
Notes:
Project work team identified and assigned.
Dates: =ENDOF("Project Team Assignment") - 09/21/2010
Duration: 4 days
Notes:
Project charter & Statement of Work signed off by Project manager and project Sponsor.
Dates: =ENDOF("Project Charter and SOW") - 09/23/2010
Duration: 2 days
Notes:
Communication Plan signed off between Project Manager and Project Sponsor
Dates: =ENDOF("Learner Analysis: Build Survey") - 10/01/2010
Duration: 1 week
Notes:
Conduct e-mail survey
Dates: 09/24/2010 - 09/24/2010
Duration: Short
Notes:
Build survey to determine interest, comfort level and experience with Educational Technology
Dates: =ENDOF("Learner Analysis: Conduct Survey") - 10/06/2010
Duration: 5 days
Notes:
Analyze responses to determine learner needs.
Dates: =ENDOF("Learner Analysis: Analyze Responses") - 10/13/2010
Duration: 1 week
Notes:
Determine concept design for module delivery to maintain uniformity.
Dates: =ENDOF("Module Design") - 10/26/2010
Duration: 1 week, 6 days
Notes:
Content Development: Module 1
Dates: =ENDOF("Content Development: Module One") - 11/08/2010
Duration: 1 week, 6 days
Notes:
Develop Module 2
Dates: =ENDOF("Content Development: Module Two") - 11/22/2010
Duration: 2 weeks
Notes:
Develop Module 3
Dates: =ENDOF("Content Development: Module Three") - 12/03/2010
Duration: 1 week, 4 days
Notes:
Develop Module 4
Dates: 11/25/2010 - 11/28/2010
Duration: 3 days
Notes:
Make necessary changes to module 2 based on module 1 evaluation.
Dates: =ENDOF("Content Development: Module Four") - 12/16/2010
Duration: 1 week, 6 days
Notes:
Develop Module 5
Dates: 01/12/2011 - 01/13/2011
Duration: 1 day
Notes:
Make necessary changes to module 3 based on module 2 evaluation.
Dates: 02/16/2011 - 02/17/2011
Duration: 1 day
Notes:
Make necessary changes to module 4 based on module 3 evaluation.
Dates: 03/16/2011 - 03/17/2011
Duration: 1 day
Notes:
Make necessary changes to module 5 based on module 4 evaluation.
Dates: 09/27/2010 - 11/05/2010
Duration: 1 month, 1 week, 2 days
Notes:
Workshop #1 – online sign up
Dates: =ENDOF("Module One: Sign Up") - 11/08/2010
Duration: 3 days
Notes:
Assign Preparation requirements
Dates: =ENDOF("Module One: Prep Requirements") - 11/16/2010
Duration: 1 week, 1 day
Notes:
Run Workshop
Dates: =ENDOF("Module One: Run Workshop") - 11/17/2010
Duration: 1 day
Notes:
Send workshop evaluations via e-mail
Dates: =ENDOF("Module One: Evaluations") - 12/10/2010
Duration: 3 weeks, 2 days
Notes:
Workshop #2 Online Sign up
Dates: =ENDOF("Module Two: Sign Up") - 12/13/2010
Duration: 3 days
Notes:
Assign Preparation requirements
Dates: =ENDOF("Module Two: Prep Requirements") - 01/04/2011
Duration: 3 weeks, 1 day
Notes:
Run Workshop
Dates: =ENDOF("Module Two: Run Workshop") - 01/05/2011
Duration: 1 day
Notes:
Send workshop evaluations via e-mail
Dates: =ENDOF("Module Two: Evaluations") - 01/28/2011
Duration: 3 weeks, 2 days
Notes:
Workshop #3 online sign up
Dates: =ENDOF("Module Three: Sign Up") - 01/31/2011
Duration: 3 days
Notes:
Assign Preparation requirements
Dates: =ENDOF("Module Three: Prep Requirements") - 02/08/2011
Duration: 1 week, 1 day
Notes:
Run Workshop
Dates: =ENDOF("Module Three: Run Workshop") - 02/09/2011
Duration: 1 day
Notes:
Send workshop evaluations via e-mail
Dates: =ENDOF("Module Three: Evaluation") - 02/25/2011
Duration: 2 weeks, 2 days
Notes:
Workshop #4 online sign up
Dates: =ENDOF("Module Four: Sign Up") - 02/28/2011
Duration: 3 days
Notes:
Assign Preparation requirements
Dates: =ENDOF("Module Four: Prep Requirements") - 03/08/2011
Duration: 1 week, 1 day
Notes:
Run Workshop
Dates: =ENDOF("Module Four: Run Workshop") - 03/09/2011
Duration: 1 day
Notes:
Send workshop evaluations via e-mail
Dates: =ENDOF("Module Four: Evaluations") - 04/01/2011
Duration: 3 weeks, 2 days
Notes:
Workshop #5 online sign up
Dates: =ENDOF("Module Five: Sign Up") - 04/04/2011
Duration: 3 days
Notes:
Assign Preparation requirements
Dates: =ENDOF("Module Five: Prep Requirements") - 04/12/2011
Duration: 1 week, 1 day
Notes:
Run Workshop
Dates: =ENDOF("Module Five: Run Workshop") - 04/13/2011
Duration: 1 day
Notes:
Send workshop evaluations via e-mail
Dates: 04/20/2011 - 04/25/2011
Duration: 5 days
Notes:
Meet with Project team to determine best/worst practices. Summarize workshop evaluations for modules 1 through 5.
Dates: =ENDOF("Project Evaluation") - 04/28/2011
Duration: 3 days
Notes:
Complete report and necessary documentation and submit
Dates: =ENDOF("Project Closure Report")
Duration: Instant
Notes:
Close project with project sponsor
Main | |
Planning and Definition | |
| 09/01/2010 - 09/03/2010 (2 days) |
Module Development PlanMeet to decide on modules to be developed, order and mode of delivery. Project vision and scope document. |
| =ENDOF("Module Development Plan") - 09/10/2010 (1 week) |
Project PlanProject Plan Finalization |
| =ENDOF("Project Plan") - 09/14/2010 (4 days) |
AISI ApplicationApplication is developed and submitted to administration. |
| =ENDOF("AISI Application") - 09/17/2010 (3 days) |
Project Team AssignmentProject work team identified and assigned. |
| =ENDOF("Project Team Assignment") - 09/21/2010 (4 days) |
Project Charter and SOWProject charter & Statement of Work signed off by Project manager and project Sponsor. |
| =ENDOF("Project Charter and SOW") - 09/23/2010 (2 days) |
Communication PlanCommunication Plan signed off between Project Manager and Project Sponsor |
Analysis, Design & Development | |
| =ENDOF("Learner Analysis: Build Survey") - 10/01/2010 (1 week) |
Learner Analysis: Conduct SurveyConduct e-mail survey |
| 09/24/2010 - 09/24/2010 (Short) |
Learner Analysis: Build SurveyBuild survey to determine interest, comfort level and experience with Educational Technology |
| =ENDOF("Learner Analysis: Conduct Survey") - 10/06/2010 (5 days) |
Learner Analysis: Analyze ResponsesAnalyze responses to determine learner needs. |
| =ENDOF("Learner Analysis: Analyze Responses") - 10/13/2010 (1 week) |
Module DesignDetermine concept design for module delivery to maintain uniformity. |
| =ENDOF("Module Design") - 10/26/2010 (1 week, 6 days) |
Content Development: Module OneContent Development: Module 1 |
| =ENDOF("Content Development: Module One") - 11/08/2010 (1 week, 6 days) |
Content Development: Module TwoDevelop Module 2 |
| =ENDOF("Content Development: Module Two") - 11/22/2010 (2 weeks) |
Content Development: Module ThreeDevelop Module 3 |
| =ENDOF("Content Development: Module Three") - 12/03/2010 (1 week, 4 days) |
Content Development: Module FourDevelop Module 4 |
| 11/25/2010 - 11/28/2010 (3 days) |
Content Development: Module Two EvaluationMake necessary changes to module 2 based on module 1 evaluation. |
| =ENDOF("Content Development: Module Four") - 12/16/2010 (1 week, 6 days) |
Content Development: Module FiveDevelop Module 5 |
| 01/12/2011 - 01/13/2011 (1 day) |
Content Development: Module Three EvaluationMake necessary changes to module 3 based on module 2 evaluation. |
| 02/16/2011 - 02/17/2011 (1 day) |
Content Development: Module Four EvaluationMake necessary changes to module 4 based on module 3 evaluation. |
| 03/16/2011 - 03/17/2011 (1 day) |
Content Development: Module Five EvaluationMake necessary changes to module 5 based on module 4 evaluation. |
Delivery | |
| 09/27/2010 - 11/05/2010 (1 month, 1 week, 2 days) |
Module One: Sign UpWorkshop #1 – online sign up |
| =ENDOF("Module One: Sign Up") - 11/08/2010 (3 days) |
Module One: Prep RequirementsAssign Preparation requirements |
| =ENDOF("Module One: Prep Requirements") - 11/16/2010 (1 week, 1 day) |
Module One: Run WorkshopRun Workshop |
| =ENDOF("Module One: Run Workshop") - 11/17/2010 (1 day) |
Module One: EvaluationsSend workshop evaluations via e-mail |
| =ENDOF("Module One: Evaluations") - 12/10/2010 (3 weeks, 2 days) |
Module Two: Sign UpWorkshop #2 Online Sign up |
| =ENDOF("Module Two: Sign Up") - 12/13/2010 (3 days) |
Module Two: Prep RequirementsAssign Preparation requirements |
| =ENDOF("Module Two: Prep Requirements") - 01/04/2011 (3 weeks, 1 day) |
Module Two: Run WorkshopRun Workshop |
| =ENDOF("Module Two: Run Workshop") - 01/05/2011 (1 day) |
Module Two: EvaluationsSend workshop evaluations via e-mail |
| =ENDOF("Module Two: Evaluations") - 01/28/2011 (3 weeks, 2 days) |
Module Three: Sign UpWorkshop #3 online sign up |
| =ENDOF("Module Three: Sign Up") - 01/31/2011 (3 days) |
Module Three: Prep RequirementsAssign Preparation requirements |
| =ENDOF("Module Three: Prep Requirements") - 02/08/2011 (1 week, 1 day) |
Module Three: Run WorkshopRun Workshop |
| =ENDOF("Module Three: Run Workshop") - 02/09/2011 (1 day) |
Module Three: EvaluationSend workshop evaluations via e-mail |
| =ENDOF("Module Three: Evaluation") - 02/25/2011 (2 weeks, 2 days) |
Module Four: Sign UpWorkshop #4 online sign up |
| =ENDOF("Module Four: Sign Up") - 02/28/2011 (3 days) |
Module Four: Prep RequirementsAssign Preparation requirements |
| =ENDOF("Module Four: Prep Requirements") - 03/08/2011 (1 week, 1 day) |
Module Four: Run WorkshopRun Workshop |
| =ENDOF("Module Four: Run Workshop") - 03/09/2011 (1 day) |
Module Four: EvaluationsSend workshop evaluations via e-mail |
| =ENDOF("Module Four: Evaluations") - 04/01/2011 (3 weeks, 2 days) |
Module Five: Sign UpWorkshop #5 online sign up |
| =ENDOF("Module Five: Sign Up") - 04/04/2011 (3 days) |
Module Five: Prep RequirementsAssign Preparation requirements |
| =ENDOF("Module Five: Prep Requirements") - 04/12/2011 (1 week, 1 day) |
Module Five: Run WorkshopRun Workshop |
| =ENDOF("Module Five: Run Workshop") - 04/13/2011 (1 day) |
Module Five: EvaluationSend workshop evaluations via e-mail |
Project Close | |
| 04/20/2011 - 04/25/2011 (5 days) |
Project EvaluationMeet with Project team to determine best/worst practices. Summarize workshop evaluations for modules 1 through 5. |
| =ENDOF("Project Evaluation") - 04/28/2011 (3 days) |
Project Closure ReportComplete report and necessary documentation and submit |
| =ENDOF("Project Closure Report") |
Project CloseClose project with project sponsor |