EDER 679: Final ProjectProfessional Development Modules for Teacher Technology Training |
Planning and Definition
Module Development Plan
09/01/2010 - 09/03/2010
Meet to decide on modules to be developed, order and mode of delivery. Project vision and scope document.
Project Plan
09/03/10 12:00:00 AM - 09/10/2010
Project Plan Finalization
AISI Application
09/10/10 12:00:00 AM - 09/14/2010
Application is developed and submitted to administration.
Project Team Assignment
09/14/10 12:00:00 AM - 09/17/2010
Project work team identified and assigned.
Project Charter and SOW
09/17/10 12:00:00 AM - 09/21/2010
Project charter & Statement of Work signed off by Project manager and project Sponsor.
Communication Plan
09/21/10 12:00:00 AM - 09/23/2010
Communication Plan signed off between Project Manager and Project Sponsor
Analysis, Design & Development
Learner Analysis: Build Survey
09/24/2010 - 09/24/2010
Build survey to determine interest, comfort level and experience with Educational Technology
Learner Analysis: Conduct Survey
09/24/10 12:00:00 AM - 10/01/2010
Conduct e-mail survey
Learner Analysis: Analyze Responses
10/01/10 12:00:00 AM - 10/06/2010
Analyze responses to determine learner needs.
Module Design
10/06/10 12:00:00 AM - 10/13/2010
Determine concept design for module delivery to maintain uniformity.
Content Development: Module One
10/13/10 12:00:00 AM - 10/26/2010
Content Development: Module 1
Content Development: Module Two
10/26/10 12:00:00 AM - 11/08/2010
Develop Module 2
Content Development: Module Three
11/08/10 12:00:00 AM - 11/22/2010
Develop Module 3
Content Development: Module Four
11/22/10 12:00:00 AM - 12/03/2010
Develop Module 4
Content Development: Module Five
12/03/10 12:00:00 AM - 12/16/2010
Develop Module 5
Content Development: Module Two Evaluation
11/25/2010 - 11/28/2010
Make necessary changes to module 2 based on module 1 evaluation.
Content Development: Module Three Evaluation
01/12/2011 - 01/13/2011
Make necessary changes to module 3 based on module 2 evaluation.
Content Development: Module Four Evaluation
02/16/2011 - 02/17/2011
Make necessary changes to module 4 based on module 3 evaluation.
Content Development: Module Five Evaluation
03/16/2011 - 03/17/2011
Make necessary changes to module 5 based on module 4 evaluation.
Delivery
Module One: Sign Up
09/27/2010 - 11/05/2010
Workshop #1 – online sign up
Module One: Prep Requirements
11/05/10 12:00:00 AM - 11/08/2010
Assign Preparation requirements
Module One: Run Workshop
11/08/10 12:00:00 AM - 11/16/2010
Run Workshop
Module One: Evaluations
11/16/10 12:00:00 AM - 11/17/2010
Send workshop evaluations via e-mail
Module Two: Sign Up
11/17/10 12:00:00 AM - 12/10/2010
Workshop #2 Online Sign up
Module Two: Prep Requirements
12/10/10 12:00:00 AM - 12/13/2010
Assign Preparation requirements
Module Two: Run Workshop
12/13/10 12:00:00 AM - 01/04/2011
Run Workshop
Module Two: Evaluations
01/04/11 12:00:00 AM - 01/05/2011
Send workshop evaluations via e-mail
Module Three: Sign Up
01/05/11 12:00:00 AM - 01/28/2011
Workshop #3 online sign up
Module Three: Prep Requirements
01/28/11 12:00:00 AM - 01/31/2011
Assign Preparation requirements
Module Three: Run Workshop
01/31/11 12:00:00 AM - 02/08/2011
Run Workshop
Module Three: Evaluation
02/08/11 12:00:00 AM - 02/09/2011
Send workshop evaluations via e-mail
Module Four: Sign Up
02/09/11 12:00:00 AM - 02/25/2011
Workshop #4 online sign up
Module Four: Prep Requirements
02/25/11 12:00:00 AM - 02/28/2011
Assign Preparation requirements
Module Four: Run Workshop
02/28/11 12:00:00 AM - 03/08/2011
Run Workshop
Module Four: Evaluations
03/08/11 12:00:00 AM - 03/09/2011
Send workshop evaluations via e-mail
Module Five: Sign Up
03/09/11 12:00:00 AM - 04/01/2011
Workshop #5 online sign up
Module Five: Prep Requirements
04/01/11 12:00:00 AM - 04/04/2011
Assign Preparation requirements
Module Five: Run Workshop
04/04/11 12:00:00 AM - 04/12/2011
Run Workshop
Module Five: Evaluation
04/12/11 12:00:00 AM - 04/13/2011
Send workshop evaluations via e-mail
Project Close
Project Evaluation
04/20/2011 - 04/25/2011
Meet with Project team to determine best/worst practices. Summarize workshop evaluations for modules 1 through 5.
Project Closure Report
04/25/11 12:00:00 AM - 04/28/2011
Complete report and necessary documentation and submit
Project Close
04/28/11 12:00:00 AM
Close project with project sponsor